Project Milestone Status

Project Milestones Status

 

Project Milestone Description (Days from Appointed Date) Planned Actual Remark Current Status
Physical Progress (%) Scheduled
Date
  Date of completion
Milestone I 159 Days 20% 22/5/2019   24/06/2019 with grace period Achieved
Milestone II 358 Days 35% 7/12/2019   30.09.2019 ahead scheduled date Achieved
Milestone III 484 Days 75% 11/7/2020   Achieved within the time frame 6-months EOT on account of COVID-19 Achieved
Scheduled Completion 730 Days 100% 13/03/2020     6-months EOT on account of COVID-19 Provisional Completion issued on 31.03.2021.